Relocation of an existing gas pipeline

To integrate a new culvert

SCROLL

Ludwig Freytag GmbH

Careful planning was required: special traffic regulations had to be organised in advance. In addition, the construction and subsequent dismantling of storage and assembly areas had to be carried out on fields with a total area of around 6,000 m2.

An eye-catching feature of this construction project was the flushing collection basin measuring 7.30 x 7.30 x 1.0 metres, which had to be constructed, maintained and dismantled.

Project manager:
André Prytamannyi, Augel
Client:
Ludwig Freytag GmbH
Place of execution:
Kasbach-Ohlenberg
Team:
3 Mitarbeiter
Execution time:
November 2020 – January 2021