In the Eifel region, Augel has been carrying out various civil engineering works on behalf of TENP since the end of April 2020. A major part of the construction project is the relocation of a DN300 gas pipeline in Auderath. For this purpose various measures around the pipe construction are carried out. Old PE-coatings are removed and various separation cuts are made. Then the pipeline route is adapted, followed by welding work in accordance with DVGW GW350 with subsequent PE re-coating of the welded seams on bare pipe sections and pipe bends.
Another special highlight is the use of our ultra-modern 3D scanner including georeferencing of the measuring points for the purpose of measurement and stock-taking after pipe construction work.